Every AI data centre project we can place on the map in Norway, Finland, Denmark and Sweden, by build stage and announced capacity. Pins link to the public sources behind them. Data as of 18 November 2026.

FAQ

What does the Nordic AI Data Centre Map show?

The map tracks 25 AI data centre projects in Norway, Finland, Denmark and Sweden that have a known site. Each pin shows the project's build stage and the capacity its developer announced, with links to the public sources behind it. Alongside the map, we summarise how each country now restricts grid access for new data centres, and list projects that have been announced without a disclosed location, such as Applied Digital's planned Finnish campus of up to 1 GW.

How much AI data centre capacity is planned in the Nordics?

The 25 mapped projects add up to about 2.9 GW of announced capacity. Only around 42 MW of it is operational for AI workloads today. Roughly 1.0 GW is under construction, 350 MW is at the early works stage (site preparation and groundworks), and about 1.5 GW is planned, permitted or leased but not yet built. Announced capacity is the developer's campus or phase target, not capacity already connected to the grid, so the real build-out will be slower and smaller than the headline figure.

Which Nordic country has the most AI data centre projects?

Finland leads on both count and capacity in our map: 13 projects and about 1.6 GW of announced capacity, including the largest single campus, Sesterce's planned 600 MW site on the former Kaipola paper mill in Jämsä. Norway follows with 10 projects and about 1.0 GW, among them Google Skien, Nscale's Narvik campus and Bitdeer's Tydal site. Denmark and Sweden each have one mapped project with a disclosed site, although both host other data centre activity that falls outside the scope of this map.

Why are Norway, Denmark and Finland restricting grid access for data centres?

Connection requests have grown far faster than the grids can absorb. Norway's Statnett received applications for about 26 GW of new consumption in 2026, three quarters of it from data centres, and paused new data centre reservations on 9 November 2026 until 1 August 2027 at the latest. Denmark's queue reached around 60 GW against a peak demand of about 7 GW, so an emergency law now puts most large data centres last. Finland has drafted priority groups that place data centres above 10 MW behind smaller users.

Can I use or cite this map?

Yes. You are welcome to link to the map, cite its figures or reference it in articles, reports and presentations, as long as you credit Gart Solutions and link back to this page. The citation and an HTML link are ready to copy in the section below the map. If you spot a missing project, a status that has changed or an error in the data, tell us through the contact form at gartsolutions.com and we will review it for the next update.
arrow arrow

Thank you
for contacting us!

Please, check your email

arrow arrow

Thank you

You've been subscribed

We use cookies to enhance your browsing experience. By clicking "Accept," you consent to the use of cookies. To learn more, read our Privacy Policy